Project 5: New Castle WWTP
- – Completion Date: Q1, 2024
-
– Summary of Work Performed
– Complete WWTP rehabilitation including new extended
aeration, Headworks Controls, RAS/WAS, Cl system integration,
Renewable Gas Turbines, Plant Water System, Bar Screen
integration, Clarifier Integration
– SCADA Sub-Contractor
– SCADA scope included Copper and Fiber
– Hardwired and Ethernet Control of VFDs
– Redundant Level 2 system
– Edge of Network Stand-Alone HMI’s
– Human Machine Interface Software
– RSLogix5000 Software
– Redundant Control Logix with CLX Remote I/O
– Hub and Spoke Redundant Network
– UL 508A Design-Build Control Panels
– Flow, Level, Pressure, and Analytical instrumentation supply and
integration